Contents

Executive Summary

1       Introduction

1.1      Introduction

2       Project Organization and Programme

2.1      Project Organization

2.2      Works Undertaken in the Construction Period

2.3      Summary of Environmental Submissions

3       Summary of EM&A Requirements

3.1      Monitoring Parameters

3.2      Environmental Quality Performance Limits

3.2      Recommended Mitigation Measures

4       Summary of Environmental Monitoring Results

4.1      Construction Noise Monitoring

4.2      Ecology Monitoring

4.3      Landscape and Visual Monitoring

4.4      Waste Management

4.5      Site Inspection

5       Summary of Environmental Quality Performance Limits

5.1      Summary of Non-compliance of Action and Limit Levels

5.2      Summary of Environmental Complaints Received

5.3      Summary of Notifications of Summons and Successful Prosecutions

6       Review of the Validity of EIA Predictions

6.1      Construction Noise

6.2      Ecological Monitoring

6.3      Landscape and Visual Monitoring

7       Review of EM&A Programme

8       Conclusion

 

 

Appendices

A.      Project Location

B.      Project Organisation

C.      Monitoring Locations

D.      Event and Action Plan

E.      Implementation Status of Mitigation Measures

F.      Graphical Plots for Noise Monitoring Data

G.      Summary of Weather Condition

H.      Record of Plant of Conservation Interest

I.        Waste Flow Table

 

  

 

 

Executive summary

Mott MacDonald Hong Kong Ltd. (“MMHK”) has been commissioned by the Gammon Engineering & Construction Company Limited to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit (EM&A) for Ocean Park Tai Shue Wan Water World Development (the Project).

The major construction works have been completed by May 2021. There were not any construction works by end of June 2021.    

This is the Final EM&A Review Report for the construction phase of the Project summarising the findings on EM&A activities during the construction period.

Result of Noise Monitoring

The summary of measured noise level (as Leq) is presented in Section 4.1. No exceedance of Action or Limit Levels for construction noise was recorded during the construction period.

Result of Ecological Monitoring

The plant species of conservation interest – One number of Platycodon grandiflorus was found in fence up area in the Reporting Period. Group 1 of Platycodon grandiflorus could not be found within the fenced area due to natural life cycle of this perennial herbaceous species, and new shoots would be expected to emerge from the underground part in the next growing season. No sign of construction activities was noted in the fence up area.

No ardeids were noted within or in the vicinity of the project area during the construction period. Details of the results are presented in Section 4.2.

Result of Landscape and Visual Monitoring

No non-compliance of Landscape and Visual monitoring was recorded in the construction period. Details of the results are presented in Section 4.3.

Record of Complaints

There were four complaints received in the construction period. Details of the records are presented in Section 5.

Record of Notification of Summons and Successful Prosecutions

There were no record of notification of summons and successful prosecution in the construction period.

 

 

 

1        Introduction

1.1        Introduction

On 27 August 2014, the Environment Impact Assessment (EIA) Report and Environmental Monitoring and Audit (EM&A) Manual (Register No.: AEIAR-184/2014) for the “Tai Shue Wan Development at Ocean Park” (the Project) was approved and an Environmental Permit (EP) (Permit No.: EP-487/2014) was issued to the Ocean Park Corporation (Project Proponent).

The current valid EP (Permit No.: EP-487/2014/A) was issued on 10 January 2018 based on the Variation of Environmental Permit No. VEP-539/2017 which comprised variation of project boundary, location of sump pit and size of rising main. The Project location is indicated in Appendix A.

Baseline monitoring for the required parameters including background noise, landscape & visual baseline review and baseline ardeid inspection were carried out between 24 October 2014 and 10 December 2014 by the environmental consultants of Ocean Park Corporation. Furthermore, the baseline monitoring report verified by the previous Independent Environmental Checker (IEC) was submitted to the EPD and endorsed in December 2014.

The previous contract (Contract No. TSW-C004) of Site Formation and Foundation Works has been completed since 31 May 2017, while the Project site was handed over to Gammon Engineering & Construction Company Limited on 31 May 2017 for the Main Building Works (Contract No. TSW-C006, the Contract). Mott MacDonald Hong Kong Ltd. (MMHK) has been commissioned by Gammon Engineering & Construction Company Limited to undertake the Environmental Team (ET) services to carry out environmental monitoring and audit for the Ocean Park Tai Shue Wan Water World Project.

The major construction works have been completed by May 2021 with the Occupation Permit obtained on 7 May 2021. The proposal for suspension of the construction phase environmental monitoring (including weekly noise monitoring and environmental site audits) by end of June 2021 was justified by the ET Leader and verified by the IEC on 23 June 2021, approved by EPD on 6 July 2021 and implemented on 6 July 2021. 

The termination of construction EM&A Programme by 31 August 2021 was proposed by the Contractor on 30 August 2021 and is supported by ET and endorsed by IEC and ER as conforming the requirements set out in the EM&A Manual. It was accepted by EPD on 29 September 2021.

This Final EM&A Review Report summarises the monitoring results and EM&A findings for the Project during the construction period of the Contract from 1 June 2017 to 31 August 2021, and is submitted to fulfil Section 11.5 of the EM&A Manual.


 

 

 

2        Project Organization and Programme

2.1        Project Organization

The project organization and contacts of key management are shown in Appendix B.  The responsibilities of respective parties are: 

Ocean Park Corporation 

Ocean Park Corporation is the Project Proponent and the Permit Holder of the EP for the development of the Project and will assume overall responsibility for the project.  An Independent Environmental Checker (IEC) shall be employed by Ocean Park Corporation to audit the results of the EM&A works carried out by the ET. 

Environmental Protection Department (EPD) 

EPD is the statutory enforcement body for environmental protection matters in Hong Kong.

Project Management Representative (PMR) of Ocean Park Corporation 

The PMR is responsible for overseeing the construction works and for ensuring that the works are undertaken by the Contractor in accordance with the specification and contract requirements. The duties and responsibilities of the ER with respect to EM&A are: 

    Monitor the Contractors’ compliance with contract specifications, including the implementation and operation of the environmental mitigation measures and their effectiveness 

    Monitor Contractors’, ET’s and IEC’s compliance with the requirements in the Environmental Permit (EP) and EM&A Manual 

    Facilitate ET’s implementation of the EM&A programme  

    Participate in joint site inspection by the ET and IEC  

    Oversee the implementation of the agreed Event / Action Plan in the event of any exceedance 

    Adhere to the procedures for carrying out complaint investigation  

    Liaison with the related government departments, ET, IEC, the Contractor and the other 

Contractors of the Project discussing regarding the cumulative impact issues.  

The Contractor 

The duties and responsibilities of the Contractor are: 

    Comply with the relevant contract conditions and specifications on environmental protection  

    Employ an Environmental Team (ET) to undertake monitoring, laboratory analysis and reporting of EM &A Facilitate ET’s monitoring and site inspection activities  

    Participate in the site inspections by the ET and IEC, and undertake any corrective actions  

    Provide information / advice to the ET regarding works programme and activities which may contribute to the generation of adverse environmental impacts  

    Submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event / Action Plans  

    Implement measures to reduce impact where Action and Limit levels are exceeded 

    Adhere to the procedures for carrying out complaint investigation  

Environmental Team (ET) 

The ET should be employed by the Contractor to conduct the EM&A programme. The ET should be managed by the ET Leader.  ET Leader should have relevant professional qualifications in environmental control and possess at least seven years’ experience in EM&A. Suitably qualified professional and technical staff should be included in the ET, and resources for the implementation of the EM&A programme should be allocated in the time under the Contract, to enable fulfilment of the Project’s EM&A requirements as specified in the EM&A Manual during construction of the Project. The ET shall include qualified botanist/ecologist for the ecological service and a Registered Landscape Architect for review of implementation of landscape and visual mitigation measures. The ET should report to the OPC and the duties should include:

    to monitor and audit various environmental parameters as required in the Approved EM&A Manual; 

    to analyse the EM&A data, review the success of EM&A programme and the adequacy of mitigation measures implemented, confirm the validity of the EIA predictions, and identify any adverse environmental impacts arising; 

    to monitor compliance with conditions in the EP, environmental protection, pollution prevention and control regulations and contract specifications; 

    to audit environmental conditions on site; 

    to report on the EM&A results to EPD, the ER, the IEC and Contractor or their delegated representatives; 

    to recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans; 

    to liaise with the IEC on all environmental performance matters, and ensure timely submission of all relevant EM&A pro forma for IEC’s approval; 

    to provide advice to the Contractor on environmental improvement, awareness and enhancement matters, etc. on site; 

    to adhere to the procedures for carrying out complaint investigation; 

    to prepare reports on the environmental monitoring data and the site environmental 
conditions; 

    to submit the EM&A report to Director of Environmental Protection (DEP) timely; 

    to review proposals of mitigation measures from the Contractor in case of exceedance of Action and Limit levels, in accordance with the Event and Action Plan; and 

    to carry out site inspection to investigate and audit the Contractor’s site practice, equipment and work methodologies with respect to pollution control and mitigation measures.

Independent Environmental Checker (IEC)   

The IEC is empowered to audit the environmental performance of construction, but is independent from the management of construction works.  As such, the IEC should not be in any way an associated body of the Contractor or the ET for the Project.  The IEC should be 
employed by OPC prior to the commencement of the construction of the Project.  The IEC 
should be a person who has relevant professional qualifications in environmental control and at least seven years’ experience in EM&A and environmental management. The duties and 
responsibilities of the IEC are: 

    to provide proactive advice to the ER and OPC on EM&A matters related to the project; 

    to review and verify the monitoring data and all submissions in connection with the EP and EM&A Manual submitted by the ET; 

    to arrange and conduct regular, at least monthly site inspections of the works during the construction phase, and to carry out ad hoc inspections if significant environmental problems 
are identified; 

    to check compliance with the agreed Event and Action Plan in the event of any exceedance; 

    to check compliance with the procedures for carrying out complaint investigation; 

    to check the effectiveness of corrective measures; 

    to feedback audit results to the ET by signing off relevant EM&A pro forma; 

    to check that mitigation measures are effectively implemented; 

    to report the works conducted, and the findings, recommendations and improvements of the site inspections, after reviewing ET’s and Contractor’s works, the ER and OPC on a monthly basis; 

    to verify the investigation result of the environmental complaint cases and the effectiveness of corrective measures; 

    to verify EM&A report that has been certified by the ET leader; and 

    to audit EIA recommendations and requirements against the status of implementation of environmental mitigation measures on site.

2.2        Works Undertaken in the Construction Period

The construction programme of the Contract commenced on 1 June 2017. The major construction works have been completed by May 2021 with the Occupation Permit obtained on 7 May 2021, while all greening works have been completed by August 2021. During the construction period, the major construction activities conducted under the Contract are summarised below:

    Set up of site office

    Site formation for haul road construction

    Foundation construction for tower crane erection

    Rock breaking and slope stabilization works

    Construction of drainage channels to slopes

    Underground manhole and drainage work

    Column and slab construction

    Cut soil slope and soil nail installation

    Construction of plant rooms, transformer room

    Bearing wall and Core wall construction

    Footing and underground utility construction

    Rising main construction

    Tree planting and landscape works

2.3        Summary of Environmental Submissions

In accordance with the EP stipulation, the required documents submitted to EPD for retention are as listed below:

    Project Layout Plans 

    Management Organization of Main Construction Companies 

    Detailed Vegetation Survey Report 

    Woodland Compensation Plan 

    Ardeid Inspection Report 

    Short-nosed Fruit Bat Inspection Report 

    Baseline Monitoring Report

    Ecological Enhancement Plan

    Visual and Landscape Plan

    Detailed Design Report for the Sewerage Facilities

    Noise Audit Report


 

 

 

3        Summary of EM&A Requirements

3.1        Monitoring Parameters

The EM&A programme of construction phase requires environmental monitoring of construction noise, ecology, landscape and visual as specified in the approved EM&A Manual. A summary of impact EM&A requirements is shown in Table 3.1.

Table 3.1: Summary of Impact EM&A Requirements

Monitoring Parameters

Descriptions

Locations

Frequencies

Construction Noise

  Leq(30min) on normal working days

  3 sets of consecutive Leq(5min) during restricted hours if necessary

NM1A and NM2

Weekly

Normal working days: (07:00-19:00 except public holiday)

Restricted hours: 19:00 to 07:00 next day, and whole day of public holiday or Sunday only when necessary

Ecology

  Monitoring of in-situ preservation of the plants of conservation interest (Platycodon grandiflorus)

 

Preservation area of Platycodon grandiflorus

Monthly

  Inspection of ardeids nest during breeding season (April to July)

Project Site

  Monitoring of ardeid night roost of in peak wintering season (November to March)

Vantage Point

  Inspection of enhancement area for ardeid roosting

Ecological Enhancement Area

N/A (No monitoring required during the construction phase)

  Monitoring on woodland compensation

Project Site

To be implemented in operational phase

Landscape and Visual

  Design, implementation and maintenance of landscape and visual mitigation measures

Project Site

Bi-weekly

Regular Site Inspection

  To monitor the implementation of proper environmental protection and pollution control measures for the Project

Project Site

Weekly

The construction noise monitoring locations as established in the EM&A Manual and the actual construction noise monitoring locations as agreed in the Baseline Monitoring Report are shown in Appendix C. The monitoring location for roosting activities of ardeid in peak wintering season is also shown in Appendix C.

3.2        Environmental Quality Performance Limits

The environmental quality performance limit for construction noise as stipulated in the EM&A Manual is presented in Table 3.2.

Table 3.2: Action and Limit Levels for Construction Noise

Monitoring Location

Action Level 

Limit Level in dB(A) 

 

Time Period: 07:00-19:00 hours on normal weekdays

NM1A and NM2 

When one or more documented complaints are received

70 dB(A) 1, 2

Note:    1. A correction of +3dB(A) was made to the free field measurement at monitoring station NM1A.
2. Acceptable noise levels for school should be reduced to 65 dB(A) during examination period

The Event and Action Plans for construction noise and landscape and visual impact during construction phase are shown in Appendix D.

3.1         

3.2        Recommended Mitigation Measures

The EM&A programme followed the recommended mitigation measures in the EM&A Manual. The EM&A requirements as well as the summary of implementation status of the environmental mitigation measures are provided in Appendix E.

 

 

 

 

4        Summary of Environmental Monitoring Results

4.1        Construction Noise Monitoring

Monitoring for noise levels due to construction work was undertaken in compliance with the EM&A manual during the construction period. The results of the noise monitoring measurement were below the Limit Level of 70 dB(A). Table 4.1 summarises the construction noise monitoring results in comparison of the Limit Level and baseline condition as reported in the Baseline Monitoring Report. Graphical plots of the construction noise monitoring data are presented in Appendix F. No exceedance of Action or Limit Levels for construction noise was recorded during the construction period.

Table 4.1: Summary of Construction Noise Monitoring Results

Monitoring Location

Baseline Monitoring Results1,

Leq (30min), dB(A)

Construction Noise Monitoring Results1, Leq (30min), dB(A)

Limit Level2, dB(A)

Range

Average

Range

Average

NM1A

52 – 63

59

56.3 – 66.0

60.3

70

NM2

50 – 67

59

47.1 – 63.0

52.2

70

Note:       1. A correction of +3 dB(A) was made to the free field measurement at monitoring station NM1A.

                2. Acceptable Noise Levels for school should be reduced to 65 dB(A) during examination period.

Additional noise monitoring was undertaken during the restricted hour period where needed. No exceedance of Limit Level for construction noise was recorded during restricted hours in the construction period. Table 4.2 summarises the results of additional noise monitoring.

Table 4.2: Summary of Additional Construction Noise Monitoring Results

Monitoring Location

Baseline Monitoring Results1,

Leq (5min), dB(A)

Construction Noise Monitoring Results1, Leq (5min), dB(A)

Limit Level2, dB(A)

Range

Average

Range

Average

NM1A

47 – 61

55

52.4 – 57.8

55.5

70

NM2

40 – 60

54 / 51 3

44.9 – 52.5

48.4

65

Note:       1. A correction of +3 dB(A) was made to the free field measurement at monitoring station NM1A.

2. Technical memorandum on noise from construction work other than percussive piling – Section 4 Table 2.

      3. As reported in the Baseline Monitoring Report, the measured average baseline noise level is 54 dB(A) for normal weekdays 1900-2300 hrs and holidays 0700 – 2300 hrs, while the noise level is 51 during night-time (2300 – 0700 hrs).

Meteorological information including temperature, humidity, wind direction and wind speed was extracted from “the Hong Kong Observatory Wong Chuk Hang Station” to provide background weather information. The meteorological data during the monitoring period is summarised in Appendix G.

4.2        Ecology Monitoring

Monthly ecological monitoring has been conducted from June 2017 to June 2021 during the construction period. Monitoring has been carried out by inspections of preservation of the plant of conservation interest, ardeid nest, ardeid night roost and ecological enhancement area within the Project Area.

Monitoring of Plant Species of Conservation Interest (Platycondon grandiflorus)

Platycodon grandiflorus is a perennial herb up to 120 cm tall. Stems erect with scarcely any branches. It is often found on sunny grassy hillslopes in bushes. Two groups of Platycodon grandiflorus were recorded in 2015’s growing season within the fenced area.

During the construction period, the preventive mitigation measures, i.e., erecting of temporary protective fencing and sign post, were found to be effectively implemented to protect the Platycodon grandiflorus from human disturbance, and there was no signs or evidence (e.g. dust coating of plant) suggesting the on-going construction activities within the Project Area has affected the health condition of the Platycodon grandiflorus. In general, the Platycodon grandiflorus was in good health condition and has been growing according to the natural life cycle. Table 4.3 summarised the special observations on the growth of Platycodon grandiflorus related to typhoon events during the construction period.

Table 4.3: Summary of special observations of Platycodon grandiflorus

Month

Special Observation

August 2017

It was observed that the whole plant prostrated on the ground due to severe typhoon HATO battered Hong Kong on 23 August 2017. The Hong Kong Observatory issued the highest Tropical Cyclone Warning Signal – Hurricane Signal No.10 and the sea level rose above normal chart datum. It was expected that severe typhoon and high sea water level caused adverse impact to the Platycodon grandiflorus because of the strong wind and its low salt tolerant. Close monitoring on the Platycodon grandiflorus was recommended.

September 2017

It was observed that new branches were grown from the stem in both two groups after the severe typhoon HATO battered Hong Kong on 23 August 2017.

October 2018

No Platycodon grandiflorus was observed due to super typhoon Mangkhut battered Hong Kong on 16 September 2018. The Hong Kong Observatory issued the Hurricane Signal No.10 and sea level rose above normal chart datum. It was expected that super typhoon and high sea water level caused adverse impact to the Platycodon grandiflorus because of the strong wind and its low salt tolerant. Close monitoring on the Platycodon grandiflorus was recommended.

November 2018

It was observed that new stems were grown in both two groups after the super typhoon Mangkhut battered Hong Kong on 16 September 2018.

As recorded during the last ecological inspection event in June 2021, it was observed that Group 2 of Platycodon grandiflorus was found to be vigorous and was in good health condition. However, Group 1 of Platycodon grandiflorus could not be found within the fenced area due to natural life cycle of this perennial herbaceous species, and new shoots would be expected to emerge from the underground part in the next growing season. The latest photo of the Platycodon grandiflorus is shown in Appendix H.

Nesting Activities of Ardeids in Breeding Season 

No signs or breeding (such as courtship, nest building, brooding, juveniles etc.) of ardeids were noted within the Project Area during the monitoring period throughout the construction phase.

Roosting Activities of Ardeids in Peak Wintering Season

No ardeids were noted roosting within or in the vicinity of the project area in the evening from an hour before sunset to nightfall during the monitoring period throughout the construction phase.

Compensation for Ardeid roosting Site

The site of proposed Ecological Enhancement Area was prepared in the first phase of construction in early 2020. In accordance with the approved Ecological Enhancement Plan, the tree planting within the Ecological Enhancement Area was being implemented and completed in July 2021. Monitoring of the compensation at the Ecological Enhancement Area will be implemented during the operation phase.

Compensation of Woodland Habitat 

The establishment of woodland compensation will be implemented after the commencement of operation.

4.3        Landscape and Visual Monitoring

Bi-weekly landscape and visual site inspection has been conducted from June 2017 to June 2021 during the construction period. Throughout the construction period, the Contractor complied with the intended aims of mitigation measures. Non-compliance was not recorded, and the Event and Action Plan for landscape and visual impact was not triggered. Only a few observations related to typhoon events were being recorded as summarised in Table 4.4, where recommended actions have been undertaken by the Contractor immediately after the events.

Table 4.4: Summary of Observations on Landscape and Visual Impact

Month

Observation

August 2017

On 23 August 2017, severe typhoon HATO battered Hong Kong. The Hong Kong Observatory issued the Hurricane Signal No.10 and sea level rose above normal chart datum, some of the trees including A0090 and A0091 were observed with yellowing of normally green leaves and large portion of drooping leaves on 25 August 2017. Close monitoring of these trees was recommended. Also, loose wire was observed, tighten up of the wire is recommended.

September 2017

On 22 September 2017, A0090 and A0091 were observed with new leaves. Although new leaves observed on these trees, close monitoring was still recommended.

October 2018

Crown damage was observed on Royal Palm due to super typhoon Mangkhut battered Hong Kong on 16 September 2018. Close monitoring of these Royal Palm was recommended.

November 2018

A few Royal Palm were found dead during reporting period due to super typhoon Mangkhut battered Hong Kong on 16 September 2018. Removal of the dead trees and tree replacement were recommended.

December 2018

Dead Royal Palms due to super typhoon Mangkhut battered Hong Kong on 16 September 2018 were removed. Tree replacement for dead Royal Palms and regular weeding in the tree protection zone were recommended.

In accordance with the approved Visual and Landscape Plan, the landscape planting and related greening works of the Project has been implemented and completed in August 2021. The monitoring of landscape planting will be conducted in operation phase.

4.4        Waste Management

The Contractor has been registered as a chemical waste producer for the Project. Construction and demolition (C&D) material sorting was carried out on site. Reuse of inert C&D material was adopted as far as practicable. Recyclable non-inert C&D materials were sorted and sent to recycling facilities. Sufficient number of receptacles were available for general refuse collection. The summary of waste generated during the construction period is presented in Appendix I.

4.5        Site Inspection

Site inspection has been undertaken by the PMR, ET and the Contractor weekly and site inspection and audit were performed by the IEC monthly from June 2017 to June 2021 during the construction period. In view of the completion of construction activities which may potentially cause significant environmental impact, the weekly site inspection has been suspended from July 2021 as approved by the EPD. During the site inspections, non-compliance was not observed by ET and IEC.

 

 

 

5        Summary of Environmental Quality Performance Limits

5.1        Summary of Non-compliance of Action and Limit Levels

No exceedance of Action or Limit Levels of construction noise or triggering of Event and Action Plan for visual and landscape impact were recorded in this period.

5.2        Summary of Environmental Complaints Received

During the construction period, a total of four cases of environmental complaints were received regarding construction noise issue. Three of the complaints were considered unlikely to be related to the construction works of the Project, while one of the complaints was considered as project related. The complaint investigations are summarised in Table 5.1.

Table 5.1: Summary of Complaint Investigations  

Date of Complaint

Descriptions

Result of investigation

Actions / Recommendations

3 March 2018

The complaint was about noise generated by construction equipment and construction vehicles movement at midnight from the construction site of Ocean Park Tai Shue Wan Water World Project.

  As Shum Wan Road experienced congested traffic during daytime, the planned concreting works had been extended beyond 19:00.

  Referring to the information provided by the site team, no works was carried out during the incident period.

  It is noted that the Contractor obtained a valid Construction Noise Permit (CNP) permitting the use certain powered mechanical equipment (PME) including PME for concreting works during restricted hours between 23 November 2017 and 16 May 2018. The listed PME and no. of units have been strictly followed to CNP.

  The complaint was unlikely to be related to the construction works on the Project site due to no construction works was carried out during the incident period.

Although the complaint was considered invalid with respect to the Designated Project, the Contractor was reminded to observe all conditions stated in the relevant valid CNPs and implement all necessary noise mitigation measures identified in the EM&A Manual.

16 March 2018

The complaint was about traffic noise at Nam Long Shan Road related to Ocean Park night time operation.

According to the complainant, construction vehicles travelled along Nam Long Shan Road in the direction of Ocean Park for the past few years between the hours of 01:00 and 04:00. Furthermore, it was suspected that some of the vehicles were garbage trucks, but according to FEHD’s reply, no garbage pick-up was conducted during this period.

  No construction vehicles accessed from Nam Long Shan Road to Project Site since the commencement of this contract (TSW-C006).

  The site entrance at Nam Long Shan Road led to the upper part of the sewage rising main under this project. However, there were no night works for this area since the commencement of this contract (TSW-C006).

  Based on the above information, the complaint was considered unlikely to be related to the construction works at the project site.

Although the complaint was considered invalid with respect to the Designated Project, the Contractor was reminded to observe all conditions stated in the relevant valid CNPs and implement all necessary noise mitigation measures identified in the EM&A Manual.

21 August 2019

The complaint was about construction noise related to the construction site of Ocean Park at Tai Shue Wan.

According to the complainant, works of the construction site at Ocean Park Tai Shue Wan on Shum Wan Road continued between the hours of 19:00 and 01:00.

  It is noted that the Contractor obtained a valid Construction Noise Permit (CNP No. GW-RS0726-19) permitting the use of certain powered mechanical equipment (PME) during restricted hours (1900-2300 hours and 2300-0700 hours) between 7 August 2019 and 1 February 2020.

  During the period mentioned in the complaint, the Contractor carried out various activities in accordance with the abovementioned CNP including concreting work and glass installation. In addition and also in accordance with the CNP, the Contractor carried out the cross road excavation. The PME that was deployed during 19:00-23:00 included one no. of excavator, tower crane concrete lorry mixer, vibratory poker (hand-held, electric) and stationary concrete pump separately Also, one no. of forklift was deployed after 23:00.

  Based on the above information, the complaint was considered to be related to the construction works at the project site.

  The use of PME by the Contractor during the restricted hours of 19:00 to 01:00 has compiled with the listed PME and no. of units stipulated in the abovementioned CNP. Thus, there were no evidence on any non-compliance with the relevant EP conditions or the CNP conditions.

Mitigation measures were implemented as below:

  The contractor has re-visited the installation sequence to minimizing the need of night-time operation as well as minimizing noise nuisance to the public in vicinity.

  Not to use the generator whenever cabled electricity connection is possible.

  Strictly implement to switch off the PME when not being operated.

  Prohibit to use whistles horns and loudspeakers for site communication, only allow to use mobile phone or walkie-talkies.

  Whenever possible, not to schedule the noisy construction activity / step in night-time.

  Conduct additional noise monitoring during restricted hours i.e. 19:00 to 07:00 next day.

  The noise limit level for additional noise monitoring were identified as 70 dB(A) and 65 dB(A) in NM1A and NM2.

27 October 2020

The complaint was about construction noise related to the construction site of Ocean Park at Tai Shue Wan.

This complaint was referred by Mr TSUI from the Southern District Council. According to the complainant, works of the construction site at Ocean Park Tai Shue Wan were conducted after 00:00. The complainant expected all works that generate construction noise could be conducted during daytime.

  It is noted that as of 22 October 2020, there was no works conducted after 23:00 in October 2020 at the Ocean Park Tai Shue Wan Water World Project construction site.

  It is noted that the Contractor obtained a valid Construction Noise Permit (CNP No. GW-RS0347-20) permitting the use of certain powered mechanical equipment (PME) during restricted hours between 29 May 2020 and 27 November 2020.

  Based on the above information, the complaint was unlikely to be related to the construction works on the Project site due to no construction works carried out during the incident period.

Although the complaint was investigated following the procedures stated in the EM&A manual and no irregularity was found, the Contractor was reminded to observe all conditions stated in the relevant CNPs and implement all necessary noise mitigation measures identified in the EM&A Manual.

 

5.3        Summary of Notifications of Summons and Successful Prosecutions

No notifications of summons or successful prosecution were received during the construction period of the Project.

 

 

 

 

6        Review of the Validity of EIA Predictions

6.1        Construction Noise

It was predicted in the EIA report that with the implementation of good site practices and mitigation measures including the use of quiet PME and movable noise barriers in place, there would be no residual construction noise impact exceeding the relevant noise criteria at all noise sensitive receivers (NSRs).

Throughout the construction phase, construction site mitigation measures were properly implemented without any non-compliance observation during site inspections. The construction noise monitoring results remained below 70 dB(A) demonstrating that no Limit Level exceedance was recorded throughout the construction EM&A programme. This is in-line with the EIA predictions.

6.2        Ecological Monitoring

The potential ecological impacts of the Project as predicted in EIA include habitat loss, impact on plant species of conservation interest, impact on ardeid’s breeding and roosting, and disturbance impact on fauna. It was predicted that with implementation of the recommended mitigation measures for the project, all residual ecological impacts were anticipated as minor to negligible.  

During the construction phase, mitigation measures proposed in the EIA report were implemented as inspected during site audits for ecological monitoring, such as erection of the protective fencing for the plant species of conservation interest. It was observed that the ecological impacts have been minimised as per the EIA predictions. Monitoring on the effectiveness of the compensatory measures would be conducted during the operation phase in accordance with the relevant approved submissions/plans under the EP.

6.3        Landscape and Visual Monitoring

The EIA report has predicted that with the implementation of proposed landscape and visual mitigation measures, the anticipated impacts would be generally moderate adverse to insubstantial during construction phase. Overall, the EIA report concluded that the landscape and visual impacts are acceptable with mitigation measures.

During the construction phase, the landscape and visual mitigation measures were compiled by the Contractor as observed from site inspection for landscape and visual monitoring. No major environmental deficiency in landscape and visual mitigation measures or triggering of Event and Action Plan for landscape and visual impact were recorded throughout the construction period. The landscape and visual impacts were mitigated by provisional of planting and greening upon completion of construction as predicted in the EIA.

 

 

 

7        Review of EM&A Programme

The EM&A programme requires construction phase monitoring for noise, ecology, landscape and visual aspects. All monitoring works were conducted as scheduled. The EM&A programme is effective in monitoring impacts arising from the Project. The overall performance and cost effectiveness of the monitoring methodology adopted were deemed effective.

Throughout the construction phase, observations and deficiencies recorded during site inspections were reflected to the Contractor immediately and relevant follow-up actions were being implemented timely. This effectively prevented potential significant environmental impacts from the construction activities. The weekly environmental site inspections also ensured that all the environmental mitigation measures recommended were effectively implemented. With implementation of the recommended environmental mitigation measures, the environmental impacts of the Project were considered environmentally acceptable.

The recommended environmental mitigation measures, as included in the EM&A programme, effectively minimised the potential environmental impacts from the Project as no environmental non-compliances were recorded. Also, the EM&A programme monitored the environmental impacts from the construction activities effectively and ensured proper implementation of the mitigation measures. There is no recommendation for the improvement of the EM&A programme.

 

 

8        Conclusion

The EM&A programme for construction of the subject works was performed from 1 June 2017 to 31 August 2021. Monitoring of construction noise, ecology, landscape and visual impacts for the Project were conducted as scheduled in the construction period. All monitoring and audit results and findings in the construction period were checked and reviewed. 

Construction noise monitoring results revealed that the noise levels at NSRs during construction were similar with that recorded during baseline monitoring. No exceedance of Action or Limit Levels of construction noise was recorded. On the other hand, ecological monitoring inspections revealed that mitigation measures proposed in the EIA were implemented and ecological impacts were minimised as per EIA predictions. For visual and landscape impact monitoring, there was no triggering of Event and Action Plan during the reporting period. No notification of summons of successful prosecutions were received or made against the subject works of the Project during the construction period.

Environmental complaints received during the construction period are related to construction noise. The complaint investigation results have shown that most complaints were considered unlikely to be related to the construction works of the Project. For the single complaint that was considered as project related, the investigation result demonstrated that the Contractor complied with the relevant EP conditions or the CNP conditions.

The overall EM&A programme to examine the potential environmental impacts of the Project and evaluate the predictions of the EIA report has provided solid proof that it has been working well according to the intention of the EIA framework in Hong Kong.